2020 Asphalt Project, Location #3

Location #3 of the 2020 Asphalt Resurfacing project is 3rd Street, between 5th and 16th Avenues.

The project will include asphalt removal and replacement.  Other work will include pavement patching, curb repairs, sidewalk improvements, driveway repairs, drainage improvements, and other related work.

This project is funded through local funds, including tax funds for electric and gas usage. 

This location was chosen because the existing pavement base is in adequate condition, meaning it doesn’t need reconstructed, however the pavement surface needs replaced.

Construction Progress:  As of October 19th this project is 99% complete.  The Contractor is waiting on their subcontractor Heritage Landscaping to complete a retaining wall on 3rd street.  Expected to be completed by the end of October. 

Contractor:  Centennial Contractors of the Quad Cities, Inc. 

Capital Improvement Project #1340

Funds:  

  • Tax on Electric & Gas Usage $700,000

Contact:  Darrel Preston, Construction Manager