2019 Trenchless Water Main Project, Location #1

The first location of the 2019 trenchless water main project is 8th Street, North of 32nd Avenue.

The project will include trenchless water main construction, including services. Other work will include pavement patching, sidewalk repairs, and landscaping as necessary.

This project is funded through local utility revenue.

This project was chosen due to the need to replace the discolored water mains.

Timeline: Fall 2019

Contractor:  Legacy Corporation of IL 

Capital Improvement Project: #1315

Funds:

•    Water $50,000

Contacts: Darrel Preston, Construction Manager

                 (309) 524-2355

                dpreston@moline.il.us

                Chad Collins, Engineering Technician II

                (309) 524-2359

      ccollins@moline.il.us