2019 Patching Program, Location #2

Moline’s 2019 Patching and Sidewalk Program will include 3 major patching locations.

Location #2 is 60th Street, south of 34th Avenue. As part of this project, deteriorating pavement will be removed and replaced as necessary.

This project is being funded with Local Options Sales Tax.

Timeline: Spring / Summer 2019

Contractor: Centennial Contractors of the Quad Cities, Inc.

Capital Improvement Project: #1322

Funds: Amounts listed below reflect the total cost for all patching and sidewalk locations.

•    Local Options Sales Tax $1,030,000

•    Water Funds $220,000

•    WPC Funds $125,000

Contacts: Darrel Preston, Construction Manager

                 (309) 524-2355 

  dpreston@moline.il.us

                 Erin Burner, Engineer Technician II

                (309) 524-2367

                ebruner@moline.il.us