Radar Road Water Main Extension, Phase II

Radar Road Water Main Extension includes extending a 12” ductileiron water main south from the end point of the 2018 project, approximately1,000’.

This new water main is necessary to allow for future developmentsouth of the QC Airport.

This project is being funded through utility revenue.

Timeline:  Fall 2019

Contractor:  T.B.D.

Capital Improvement Project:  #1324

Funds:  

·       Water Funds  $115,000

Contact:  Darrel Preston, Construction Manager


                (309) 524-2355