17th Avenue Reconstruction Project

17th Avenue Reconstruction Project

The 17th Avenue reconstruction project will take place between 10th and 11th Streets. 

The project will include pavement replacement with an asphalt pavement structure, sidewalk repairs, driveway repairs, drainage improvements, water main replacement, sanitary sewer replacement, and other associated work.

This project will be constructed using tax funds for electric and gas usage. 

This project was chosen due to the need to replace the sanitary sewer and water main. 

Timeline:  Summer 2018

Contractor: Valley Construction Company

Capital Improvement Project:  #1286

Funds:  

  • Tax on Electric and Gas Usage $235,000
  • Water $105,000
  • Sanitary Sewer $170,000
  • Stormwater $15,000

Contact:  Darrel Preston, Construction Manager

                 (309) 524-2355